The Project
Impressions from the project process
Project Information
Requirements
Using PERI swivel tables for the perimeter deck shoring is allowing Largo Concrete personnel to quickly and safely cycle forms with the PERI Lifting Fork, while the PERI GRIDFLEX Shoring System provides an easy infill system for the deck shoring. The swivel tables employ custom handrails that exceed the California OSHA standards to meet the high safety requirements of the general contractor, Lendlease Corp. PERI LPS Lightweight Climbing Enclosure was added on the east side of the building as protection for patrons of the Metrolink station below. Furnished complete with hydraulic lifting accessories, the LPS Screen uses higher standard mesh screens, plywood flaps, and rubber gaskets to again meet the general contractor’s increased safety requirements. Throughout the project, partnering with PERI has enabled Largo Concrete to leverage the experience and expertise of both firms to meet the general contractor’s high requirements for safety based on its history of successful projects in the New York market.
Solutions
LPS light protection screen to secure the perimeter above the train station GRIDFLEX lightweight slab formwork as the shoring system UNIPORTAL tables for the cantilevers and round edges
Working with the PERI Engineering Team, Largo Concrete Inc. was able to create a ‘project-specific’ solution to hand-set formwork on the perimeter edge of 1200 South Figueroa towers utilizing the PERI LPS Screen as an alternate method of protecting the perimeter areas of the typical tower floors.
Loay Hanthel
Engineering Manager
Are you working on a project like this?
Call us on +1 410-712-7225 to discuss your requirements further.
Los Angeles, CA United States