The Project
Impressions from the project process
Project Information
Requirements
The contractor used 38,000 ft2 of PERI’s SKYDECK drophead shoring system as well as three levels of PEP Ergo shoring to construct the six-level post-tensioned parking structure in just five months while also providing the required as-cast ceiling finish resembling traditional plywood. Fast, clean, and simple, the SKYDECK system requires a smaller crew to erect and strip compared to other systems. In addition, PERI UP Flex Stair towers were used to provide access to the six-story structure throughout the duration of the project.
Solutions
PERI SKYDECK panlized slab formwork system PERI UP Flex Stair Tower


Fernando Grajeda
Superintendent
Are you working on a project like this?
Call us on +1 410-712-7225 to discuss your requirements further.
San Diego, CA United States


San Diego, CA United States