Using two PERI Self Climbing Systems enabled Clark Concrete’s crews to frame the elevator walls of both the north and south cores simultaneously and without relying on the single tower crane.

CEB Tower at Rosslyn Central Place
Arlington, VA, United States

This 31-story commercial office building is being constructed atop the Rosslyn Metro Station directly across the Potomac River from Washington, D.C. When completed, it will be the tallest in the metropolitan area and will feature a public observation deck offering unparalleled views.

Customer
Clark Concrete, LLC. 

 

 

The Project

Impressions from the project process

Project Information

Wigberto Hernandez, Carpenter Foreman
Wigberto Hernandez, Carpenter Foreman
Wigberto Hernandez
Carpenter Foreman
The PERI Self Climbing System is the best wall framing system I have used in terms of safety. My crew and I are very appreciative of the thought that went in to this system to make it safer for us to perform our work.